By Charles Nwoke
Governor Francis Nwifuru of Ebonyi State has accused the Transmission Company of Nigeria (TCN) of frustrating his administration’s efforts to industrialise the state through delays in developing a dedicated energy grid.
The governor stated that prolonged approval processes and feasibility studies by TCN have stalled critical power projects, despite agreements with relevant stakeholders and substantial payments made by the state government.
Nwifuru spoke during the 2025 State Thanksgiving Service held on Sunday at Centennial City, Abakaliki. He expressed frustration over what he described as avoidable bureaucratic bottlenecks.
He disclosed that about 90 per cent of the cost of the Amasiri transmission line project has already been paid to the contractor, yet work has not progressed as expected.
According to the governor, electricity remains the biggest obstacle to Ebonyi State’s industrial development.
“The problem I am facing in industrialising our dear state till now is electricity, and the Transmission Company of Nigeria is compounding the problem,” Nwifuru said.
He explained that TCN advised the state not to wait for the Federal Government to deliver the project, prompting the state to fund the project directly in collaboration with the agency.
Despite this decision, the feasibility study for the proposedkV0 KVA transmission line has continued for over a year.
“Since last year, the feasibility study has been ongoing, and TCN is handling it. This is something a private firm can complete within two or three weeks,” he said.
Nwifuru also criticised the slow pace of work on the Amasiri power transmission line, a project awarded during the administration of former President Goodluck Jonathan.
He said the state paid more than N1.7 billion about two years ago after TCN requested the funds, yet the project remains incomplete.
“We entered into a contract, and till today the job is still not completed,” he said.
The governor said the delays have forced his administration to suspend plans to establish industries in the state, noting that the current electricity allocation to Ebonyi State cannot support industrial operations.
“That is why I have not built any industries in the state. Industries need electricity to function, and what we receive is not enough,” he said.
He added that both TCN and the contractor have contributed to the delays, despite the state government’s willingness to finance the projects.
Nwifuru also accused the contractors of offering repeated excuses, including frequent foreign trips, when pressed for explanations.
He said TCN recently cited unpaid compensations as another obstacle but failed to identify any affected persons or structures.
“I told them I was ready to pay. I asked them to show us the buildings or persons to be compensated, but they have not shown us anyone,” he said.
Meanwhile, the Ebonyi State Government has inaugurated an economic team to explore options for establishing another cement factory or reviving the moribund Nigercem Cement Factory in Nkalagu, Ishielu Local Government Area.
The government is also considering reclaiming the facility from its core investor, the Ibeto Group of Companies, as part of efforts to stimulate industrial growth in the state.