Ifeanyi E Ihegwuruike
About eight streets linked to the erosion wreaked Ovom Street in Aba North Local Government Area of Abia State have been rescued through the Ovom Erosion Control Project being handled by OK and JOEL Engineering Services Limited.
AlphaTimes visited the site at the Ovom Erosion Control Project at Ovom Street and reports that the gully erosion which was 15-18 feet deep at some points and about 30 metres wide, has been covered with the laterite.
Site engineer of Ovom Road Erosion Control and a director with OK and JOEL Engineering Services Limited, Anthony Anyim said the company in charge of the project, said that the main aim was to control the devastating erosion that has chased many residents from their homes.

Anyim stressed that the company started by filling up the worn away areas with laterite soil, which, as you can see now, we’ve gotten to the level where the existing ground was before.
According to him, “We’ve done a sizeable drainage that’s 1.2 by 1.2 metre, to contain and control the floodwater that has been a problem here. Now, all these streets, about seven to eight of them, you see have works ongoing.
“What we’re doing is to create better access roads and drainage that will help to carry floodwaters from those streets into the main flood control drainage that we’ve built already.
“We are aware that the floodwaters from the streets are contributing to the erosion eating up the place. So, we’re doing 750 by 750 drainages from those streets that will eventually empty into the 1.2 by 1.2 metre drainage that will eventually take the floodwaters into the nearby river there.

“We believe this is enough because we’re in the better part of the rainy season, and there’s not much erosion when it rains. So, by the middle of next week, we’ll start concrete pavement, which we’ll use to finally seal the fate of the erosion menace here in this area completely.”
Speaking further, he said, “We’ll do the concrete pavement from the point of the erosion to the connection point with Pepple’s road, and as you can see, our batching plant is ready.
“So, once we start the concrete pavement, in less than two months, the whole place will be ready for use.”

AlphaTimes gathered from the majority of the residents that the almost complete project has brought hope back to many property owners who once thought that their buildings will be worn away by the rampaging gully erosion.